SEA WOLF 1 - Zeyport, Turkey - Starlink. Sharewave & Peplink Installation


Field Disptach -SEA WOLF 1 

Zeyport Port, Istanbul | 7–8 November 2025

Project Overview

Global Satcoms successfully completed a multi-system communications installation onboard SEA WOLF 1, covering Starlink, Peplink, and Waveshare systems. Despite short port time, boarding delays, and full night operations, all installations, cable work, cabinet organisation, and system validation were finished within the vessel’s 12-hour operational window.

Project Details

Vessel:                         SEA WOLF 1
Location: Zeyport Port, Istanbul, Turkey
Service Dates: 7–8 November 2025
Client: Orbyt Global
Category: Maritime Communication Systems

Scope of Work

  • Starlink Installation Support
  • Peplink System Installation
  • Waveshare System Setup
  • Cabinet Cable Organisation
  • GPS Temporary Cable Routing
  • Remote Testing and System Validation

Challenges & Operational Constraints

  • Vessel only in port for 12 hours
  • Night-time operation with continuous work through early morning
  • Delays during motorboat access to vessel
  • Missing GPS cable route required immediate temporary solution
  • Coordination required between engineer, vessel electrician, and remote support

Systems Installed & Commissioned

  • Starlink high-speed satellite communication system
  • Peplink routing and network optimisation system
  • Waveshare communication hardware

Work included cable routing and terminations, mounting, cabinet organisation, heat-shrink protection, temporary GPS cable installation, and remote system validation.

Timeline of Activities

7 November 2025

  • Port access and security procedures completed
  • Motorboat boarding at 18:50
  • Coordination with captain and electrician
  • Inspection of all equipment
  • Mounting poles installed by vessel electrician
  • Starlink & Peplink cable routing and termination
  • Heat-shrink protection applied (completed at 01:20)

8 November 2025 – Overnight Work

  • Cabinet cable reorganisation completed
  • Remote-assisted connection checks
  • Missing GPS route identified
  • Temporary 15m GPS cable installed
  • Permanent routing instructions issued
  • Final validation at 06:00
  • Disembarkation and travel

System Status Overview

System           Status            Notes
Starlink              Operational         Fully installed and tested
Peplink Operational Configuration validated
Waveshare Operational Integrated successfully
GPS Operational Temporary cable; permanent route recommended

Lessons Learned

  • Essential to confirm cable routes before engineer mobilisation
  • Night operations require full remote support availability
  • Port logistics such as motorboat transfers require buffer time
  • Spare cabling prevents mission delays
  • Coordination with vessel electricians is key to maintaining workflow

Final Outcome

All systems were successfully installed and validated within the vessel’s restricted 12-hour stay. The engineer worked overnight to meet deadlines, and the vessel crew confirmed acceptance of all works. SEA WOLF 1 now operates with an enhanced, modernised, and fully reliable maritime communication suite.